BS 7671 sets out initial verification of new work and periodic inspection of existing installations, including the dead and live tests that confirm an installation is safe.

Part of BS 7671 is devoted to inspection and testing — the procedures that confirm an installation is safe, both when newly installed and periodically throughout its life.

Two contexts

  • Initial verification — carried out on new installations and major alterations before they are put into service, resulting in an Electrical Installation Certificate (EIC).
  • Periodic inspection — carried out at intervals on existing installations, resulting in an Electrical Installation Condition Report (EICR).

The core tests

Whether initial or periodic, testing follows a logical sequence of dead tests (with the supply isolated) and live tests (with the supply on):

  • Dead: continuity of conductors, insulation resistance, polarity.
  • Live: earth fault loop impedance, RCD operation, prospective fault current.

Why the sequence matters

The order is a safety measure — dead tests confirm the installation is safe to energise before live tests begin. Following the model forms and procedures ensures results are consistent, comparable and defensible. For what this looks like on a real EICR, see what happens during an EICR.

This article provides general guidance and distinguishes legislation, British Standards and good practice. It is not legal advice. Always confirm the specific duties applying to your property and tenure.

Speak to a compliance engineer

The quickest way to get started is a quick call. We'll tell you exactly what you need.

We use essential cookies to run this site. With your consent we also use analytics and marketing cookies to improve the site and measure our advertising. See our cookie policy.